Take the 2-minute tour ×
Super User is a question and answer site for computer enthusiasts and power users. It's 100% free, no registration required.

In Microsoft Project 2007, I can't work out why my tasks are scheduled to finish later than I would expect for the Duration I put in.

I enter a task with a start date on a Monday and a 1-day duration, and it shows the Finish as Tuesday.

Task Name     Duration  Start       Finish
Do Something     1 day  12/04/2010  13/04/2010

How can I set this up so a one-day task takes one day, and not one-and-a-bit? I want a one-day task that starts on a Monday to finish on the Monday.

share|improve this question
add comment

1 Answer

up vote 0 down vote accepted

Ah, I found it.

In Change Working Time, the working day in the Work Weeks tab details was defined as being 0900-1200 and 1400-1700, so that's only 6 working hours a day, but the Options had the setting Hours per day set to 8 hours.

That meant a task entered for 1 day, which equals 8 hours, clearly can't fit in on 'real' 6-hour day.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.