Is there a way to create a relative Gantt in MS project, that is a Gantt that doesn't have a defined start date, just amount of time required for each task?

link|improve this question

25% accept rate
feedback

migrated from stackoverflow.com May 14 '10 at 22:23

This question came from our site for professional and enthusiast programmers.

2 Answers

Perhaps you didn't want to show specific dates, a generic 'duration' schedule? This is referred to as an Ordinal timescale in Primavera's schedule software. MS Project achieves this by change the timescale labels to show 'month 1', 'month 2', etc. -- then just hide any date columns and you have a generic schedule.

link|improve this answer
Is it possible to not have the month X as well? Just the duration is what I'm looking for. – SyRenity Aug 23 '10 at 17:03
feedback

You can do that only if your project structure does not use hard constraints (MSO, MFO...). This will allow you to just change the project start date and all the project to be rescheduled relative to that date.

link|improve this answer
The idea is just to see the duration - without actual start date. This Gantt goes to marketing, so it quite uncomfortable to update it every time. – SyRenity Aug 23 '10 at 17:03