I use Tasks in Outlook 2007 and I like to enter new tasks using the textbox in the To-Do Bar (ie. without actually opening a new Task window). This automatically sets today's date as the due date for the new task, which is unhelpful in most cases. Most of my tasks don't have a specific due date, but from the next day on the task appears in red, distracting my attention from the few tasks that really are overdue. I then have to open the Task and manually clear its due date. Is there any way I can set the default due date to "none" for tasks that I enter from the To-Do bar?

link|improve this question

36% accept rate
feedback

1 Answer

up vote 3 down vote accepted
  • Go to your tasks
  • Right click the flag on a task
  • Click "Select Quick Picks"
  • Change the selection to "None" or "No Due Date"

Future quick checks will not have a due date.

link|improve this answer
Excellent, thank you! That does exactly what I want, though the menu item is called "Set Quick Click" for me. – EMP Jul 23 '10 at 0:57
feedback

Your Answer

 
or
required, but never shown

Not the answer you're looking for? Browse other questions tagged or ask your own question.