When I am in the tasks screen I can check off tasks and they will disappear.
However, if I am in the calendar view, they show up with a line through them rather than disappear. How can I change this?

share|improve this question

The To-Do List has a filter applied that -by default - removes tasks that have a completion date or Flag Completed Date.

To-Do List Filter Dialog

The Calendar view doesn't have the same sophisticated filter, but you can hide completed tasks.

  • Go to the Calendar view.
  • Right-click in the empty area below the last task.
  • Select Arrange By and uncheck Show Completed Tasks.
share|improve this answer
    