I noticed that tasks in my MS Project in Gantt view turned red, out of my control. Can you help to explain what might happen?

link|improve this question
feedback

migrated from stackoverflow.com Apr 8 '11 at 9:45

This question came from our site for professional and enthusiast programmers.

1 Answer

It's becuase they are on the critical path of your project.

Check out articles on Earned Value, Future Value etc to see how it calculates it

-Ben