I've started using Project 2007 to map out my workload.

I'm thinking about upgrading to 2010. What I would like to know is if there is any timesheet functionality in Project 2010 that would allow me to enter my actual working time on a task against what was planned?

Thanks

link|improve this question
feedback

1 Answer

Project server 2010 does, I'm not sure about project itself however

check out the live demo here

http://go.microsoft.com/?linkid=9713654

link|improve this answer
feedback

Your Answer

 
or
required, but never shown

Not the answer you're looking for? Browse other questions tagged or ask your own question.