I'd like to put my schedule into org-mode, so that I can see my classes in the agenda. I have different classes, repeated every week, all of them taking 90 minutes. I was thinking about something like this:

* My schedule
** Differential equations
   <2012-10-04 Thu 11:45 +1w>--<2012-10-04 Thu 13:15 +1w>

However, there are two problems: I can see only the next instance in the agenda, and I can't see the ending time. Any ideas?

share|improve this question

migrated from stackoverflow.com Sep 29 '12 at 17:54

This question came from our site for professional and enthusiast programmers.

1 Answer 1

up vote 3 down vote accepted

I'm pretty sure you're searching for the org-diary-class, mentionned in the Worg faq.

Your exemple would then be (assuming classes end on December 20th) :

** 11:45-13:15 Differential equations
   <%%(org-diary-class 10 4 2012 12 20 2012 2)>

You can add weeks where there are no classes after the last number (which is 2 for tuesday).

If you don't like having the time in the headline, you can use :

%%(org-diary-class 10 04 2012 12 20 2012 2) 11:45-13:15 Differential Equations

Last time I checked, it required %% not to be indented, so I guess each of these awesome solutions have their slight drawback.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.