Take the 2-minute tour ×
Super User is a question and answer site for computer enthusiasts and power users. It's 100% free, no registration required.

I would like the start date of a dependent task to start the next day, even if the predecessor task finishes a little early the previous day. Unfortunately the successor task always starts (assuming an FS dependency) immediately after the predecessor task.

Sample

In this example, even if Task 3 finishes on Jan 2 at 12:00 PM, I do not wish for the Client review task to start on Jan 2, instead to start the starting (8:00 AM) of the following day. Is there a way I can force this?

Thanks, Sean

share|improve this question
add comment

1 Answer

There is no way to do this in MSP. The nearest your can get, assuming for example that all your tasks are <1 day in length, is to make the second task a predecessor of the first using a start-start relationship with a lag of 1d. In effective this says "start the second task one day later than the start of the first task, no matter on which day Task 1 starts...

But that is unlikely to be useful as if Task 1 starts a 10:30 on Day 1, Task 2 will start at 10:30 on Day 2, not 09:00 on Day 2.

Or you can muck around with Start No Earlier than constraints on all the subsequent tasks, but that is going to be a PITA for anything more than one instance.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.