The tag has no wiki summary.

learn more… | top users | synonyms

1
vote
1answer
286 views

ms project 2010 roll up task, milestones hidden behind tasks

I am trying to use roll up tasks in project, however my milestones are being hidden behind the tasks, is it possible to force the milestone tasks to the front view?
1
vote
1answer
65 views

MS Project 2010 Base calendar is ignored

I'm using Project 2010 with a project base calendar that has been loaded with exceptions for company holidays. However, when I add tasks to it and resource load them, it is ignoring the base calendar ...
1
vote
1answer
74 views

Automate Microsoft Project 2010 launch

I am looking for some way for automate Microsoft Project 2010 launching when exported file is created by another project management software. Is it possible to force MSP2010 to open the file?
0
votes
1answer
148 views

Cannot install Microsoft Project 2010

I have a Windows 7 x64 OS. I have installed Microsoft Office 2010 32 bit in it. When I tried installing Project 2010 it failed. I have run it as administrator but still no progress. I get these 2 ...
0
votes
1answer
13 views

How can a show a task that has a window for completion

I have several tasks within a project that take 2 days but have a three month window in which to complete how do I show this on my gantt chart?
0
votes
1answer
73 views

summary tasks in Microsoft project 2010

if i add a summary task in microsft project planning how do i make 3/4/5..... tasks below under it. i have created summary tasks but the tasks beneath them are not consistent. for example week ...
0
votes
1answer
229 views

How to force a dependent task to start the next day?

I would like the start date of a dependent task to start the next day, even if the predecessor task finishes a little early the previous day. Unfortunately the successor task always starts (assuming ...
-1
votes
1answer
9 views

A Microsoft Project file, mpp, hangs or crashes Project 2010

I have an MPP file, totally created in Project 2010, either hangs or causes Project 2010 to crash. It seems that there's some corruption in it. I have tried downloading some (few) solutions out there, ...
2
votes
0answers
146 views

MS Project 10 & 13 - Creating Custom Gantt Chart for Resource Allocation

I have created a very basic setup to better monitor staffing and scheduling decisions for my firm. Essentially, I create one task for each new project and assign the resources that will work on that ...
1
vote
0answers
151 views

Change MS Project 2010 task text color by flag field

I want to change the text color (at least) for tasks that deliver a document. I setup the custom field "Flag 18" to show whether this line item is a document or not. I can change the gantt bar color ...
1
vote
0answers
25 views

How can I change settings on part of (divided) task?

I want to know how to split a task i several parts and how to change settings separately for each part (different color for instance). I have been working in another planning tool where this is ...
0
votes
0answers
5 views

Microsoft project assigning IDs to specific rows only

I've created a microsoft project Gantt chart with lots of rows. The rows are made up of main topics and related tasks beneath these. I want to attach an ID number to only those sub task rows so that ...
0
votes
0answers
24 views

MS Project 2010 web app won't let me create a new project. I have full access

I've just started with ms project 2010 and am looking at someone else's install. I took full control and everything seems good, but one major flaw: I can't create a new project. It says "this control ...
0
votes
0answers
29 views

change in %complete after reschedule while tasks are fixed duration in Microsoft Project

After Rescheduling a plan, if i enter a percentage lower or equal to current value, duration of task will change to its original value (value that was set before reschedule). Its wonderful that even ...
0
votes
0answers
23 views

Save gantt chart in Microsoft Project

I had draw my gantt chart in Microsoft Project 2010. After complete my job I found that I cannot save it due to my Microsoft Project 2010 is a trial version. Is there anyone know that how to save my ...