I have a setup with VimWiki, TaskWarrior/TimeWarrior and TaskWiki. Yesterday I observed, that some task wheren't tracked, because I couldn't get a timew summary of it.

When I started those task from TaskWarrior directly I got the message: You cannot overlap intervals. Correct the start/end time, or specify the :adjust hint. The task was started correctly by TaskWarrior (I could see it in the list as "active") but was NOT recognized by TimeWarrior in any way.

I tried a few things, but I can't find unpropper intervals anywhere and I can't find Information on how to use ":adjust" with TASKwarrior.

The examplary task:

Name          Value                                 
ID            10
Description   task review and push                  
Status        Pending
Entered       2018-08-21 11:55:09 (20h)             
Start         2018-08-22 08:09:31
Last modified 2018-08-22 08:09:31 (1min)            
Tags          w daily
Virtual tags  ACTIVE PENDING READY TAGGED UNBLOCKED 
UUID          afe4be48-aed6-4d1f-aba7-d748bf368868
Urgency        4.9                                  

    active      1 *    4 =      4
    tags      0.9 *    1 =    0.9
                           ------
                              4.9

Date                Modification                                                                  
2018-08-21 11:55:41 Tags set to 'w,daily'.
2018-08-21 16:10:09 Start set to '2018-08-21 16:10:09'.                                           
2018-08-21 16:25:40 Description changed from 'task review and push !!' to 'task review and push'.
2018-08-21 16:25:41 Start deleted (duration: PT15M32S).                                           
2018-08-21 16:25:42 Start set to '2018-08-21 16:25:42'.
2018-08-21 16:25:58 Start deleted (duration: PT16S).                                              

Can someone please tell me what it has to do with the "cannot overlap"-message and how to resolve it, please.

2

I know this issue is so old, it's probably solved, but for reference:

I ran into a similar problem. I'm not sure what caused it, but I think that it happened because I forgot to stop the time-tracking at some point. Timewarrior created lots of tracked days in the future. I was able to find the IDs of the days in the future by getting the tasks for the whole year

timew summary :year :id

and then deleting the tasks in the future with

timew delete @1 @2 (or whatever IDs apply)

After the deletion tasks can be tracked normally again.

| improve this answer | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.