I created a task in MS Project 2010 which starts on 14-Oct-2011
and has a duration of one day.
Project automatically sets the Finish Date to 17-Oct-2011
(because the 15th and 16th are weekend non-working days).
However my task will really finish on the same day i.e. 14-Oct-2011
, but when I set the Finish Date to 14-Oct-2011
MS Project shows the task as having a duration of 0.88
days which is wrong:
Why is this and is there a way around it?
Updated:
Had a fiddle around with the Default start/end
time values in File -> Options -> Schedule
page. I changed from 0800
/1700
to 0900
/1800
.
I then changed the project's Working Time (Project -> Working Time
) [Default]
working time for the week from:
Monday to Friday: 08:00 to 12:00 and 13:00 to 17:00
to
Monday to Friday: 09:00 to 17:00
I'm not sure why this works because the number of working hours (8) per working day hasn't actually changed.