sI have a project that I need to run 24/7 with no breaks. I need to set task start times at specific times of day. How can I do that?

IE. if task 1 takes 4 hours and task 2 takes 3 hours; how can I set task 1 to start at 6AM and task 2 at to start at 10AM?

ADDITIONAL PROBLEM: I have set the project to work through weekend but it won't schedule weekends.

5
  1. Set the project calendar (Project Tab, Project Information) to the 24 hours calendar.

  2. Turn on the display of time plus date in File > Options, General under date format.

| improve this answer | |

Your Answer